For those hapless motorists attempting the US 93 construction zones in the victor area, some relief is promised.
At a meeting of Victor businesspeople and the Montana Department of Transportation this week, officials said the paving of the new 4-lane roadway in the immediate Victor downtown area should be completed by next Friday, July 22.
Further paving is planned for the Sweathouse Creek area and in the second week of August, the 2 mile section south of the Bear Creek intersection, with the portion north of Bear Creek being paved in September. All the dates are dependent on weather and possible equipment issues.
This does not include landscaping and striping.